Crown Mountain targets 2029 construction

Crown Mountain Resources plans to submit a revised environmental application for its proposed Elk Valley coal mine by the end of 2026, with the company forecasting construction activity in 2029 if it secures environmental approval and permits.

Director of Project Development Dave Baines presented the timeline to Crowsnest Pass council August 18. The dates are company projections and are not approval commitments from provincial or federal regulators.

The proposed open-pit coking-coal mine is near Sparwood, B.C., west of the Alberta boundary. Baines said the project would operate for about 15 years, producing roughly two million tonnes of steel making coal annually and 30 million tonnes over its life.

The company changed its name from NWP Coal Canada Limited to Crown Mountain Resources on June 1. Baines said the change was meant to distinguish the project from Northback’s Grassy Mountain proposal and other coal companies with similar names.

The B.C. Environmental Assessment Office issued a Section 27 notice for Crown Mountain May 26. The notice records feedback on the application and directs the proponent on the revisions required before it can submit a clean application for further review.

Baines described the notice as a major milestone after several rounds of technical questions and changes to the proposal.

“If everything goes well, we get that submission into the government at the end of this year,” he said.

Once submitted, the revised application must pass a conformity review to determine whether it contains the required information and responds to the notice. Baines estimated that stage would take about 60 days.

An accepted application would then move into the effects-assessment stage. The provincial process provides 150 days to prepare a draft assessment report and proposed certificate, followed by a 30-day ministerial decision period, though timelines can be extended.

Baines projected provincial and federal environmental approval by the middle of 2027, permits late in 2027 or early in 2028 and construction activity in 2029.

The project has not received those approvals or operating permits.

The B.C. regulator’s 2024 public-engagement summary recorded more than 250 comments on the application.

 Concerns included selenium and water quality, wildlife habi-tat and connectivity, cumulative industrial effects, coal dust, recreation access, housing pressure and transboundary effects. The summary also recorded eight comments ex-pressing support or interest in the project’s economic potential.

Baines told council the mine’s design requires less waste rock movement than neigh-bouring operations. He said that would reduce the potential for selenium, nitrate and dust effects. Those are company claims under regulatory review.

The company estimates a peak construction workforce of about 500 over two or three years, followed by approximately 350 operating jobs.

Baines said Crown Mountain was updating its housing and employment strategy using current regional information. He told council the project could bring workers and traffic through Crowsnest Pass and create demands on housing, health care and other ser-vices.

Crown Mountain and Yaq̓it ʔa·knuqⱡi’it First Nation signed an Early Indigenous Training and Employment Initiative in June. Baines said the initiative would begin workforce planning before construction through apprenticeships, scholarships, college involve-ment and employment pathways.

He described the initiative as part of a broader relationship that includes a consent agreement. Baines said the company would not proceed without support from the First Nation, though the agreement itself was not before council.

The company is also working toward a shared prosperity agreement covering planning, development, operations and reclamation. Baines said Crown Mountain plans to trans-fer the Confluence and Sulphur Springs parcels to the First Nation for conservation and community control.

Council members asked about employment and proposed a tour of the project site. Baines said tours would remain available until the middle of October and administration agreed to help arrange one.

Council heard the update without passing a separate motion. The company’s next for-mal step is completing the revised application and demonstrating to regulators that it has addressed the May notice.